On June 14, we had a work night at school.  We washed windows, installed window screens, put up directional signs, etc.

A few weeks ago, carpet was laid in the three classrooms upstairs and in the library.  Toilets were also installed in the restrooms upstairs.  This past week, shelves for the closets were cut.

There are still a lot of things to be done like buy lockers, finish the kitchen, spread more gravel, set up chalkboards and bulletin boards, install the elevator, obtain water fountains, carpet the walls in the basement, etc. Since a number of those things can wait, we will primarily work on painting and installing the shelves, finishing the trim, installing vanities and partitions in the restrooms, and painting and finishing the doors.

Our school teachers, Matt Kratzer, Fonda Overholt, and Yvonne Stoltzfus, will be coming in the end of July to organize and put their new classrooms in order.  We are hoping to have a lot of work done by the time they come.